NASA Reworks How Science Missions Compete

Gemma Lavender Editor Science.Report

Post by Gemma Lavender

NASA Reworks How Science Missions Compete Science.Report © science.report
NASA Reworks How Science Missions Compete © science.report

NASA's Competition Model 2.0 would reshape how mission proposals are assessed, starting with a science-focused first round and shorter selection schedules; a virtual town hall is set for Monday, October 26

NASA says the selection timeline for Astro-Probes, New Frontiers and Discovery missions could shrink from 35 months to about 19.5 months under its revised competition plan. The agency expects a stronger, more mature mission at selection, while asking teams to spend less time preparing extensive proposals before their science is assessed. The Science Mission Directorate (SMD) describes the principle as competing on the science first.

Science First

Competition Model 2.0, also referred to as CM2.0, would begin by judging the science case. In Step 1, teams would submit a compelling science case, a science implementation plan and a proof-of-concept mission design. NASA says this package contains roughly half the material currently required in an Announcement of Opportunity (AO) response.

The reduced first-round burden is intended to let reviewers focus on scientific merit rather than the resources behind a proposal. NASA says principal investigators without major university or commercial backing should receive fair consideration, and NASA investigators at any NASA Center remain eligible to respond. The agency plans to introduce the changes in stages and refine them with community input. The shorter first step would not eliminate later technical and financial review; it would move detailed implementation work to a later stage.

Different Mission Paths

Flagship missions are an exception: their management process will not change under CM2.0. Following the James Webb Space Telescope, NASA conducted the Large Mission Study, which drew lessons from Webb and documented an approach for building large missions more efficiently. NASA will continue directing each flagship to a lead NASA Center; science teams and instruments will then compete through targeted solicitations.

For Astro-Probes, New Frontiers and Discovery, Step 2 would be a Mission Implementation Study (MIS). It would assess scientific merit, the merit of the science implementation and the merit of the mission implementation, with the stated aim of surfacing risks early. The study bridges pre-Phase A and Phase A. Studies would be carried out with Goddard Space Flight Center or the Jet Propulsion Laboratory (JPL). Depending on the selected science, NASA's Science Mission Directorate may award a New Frontiers or Discovery study to Johns Hopkins University Applied Physics Laboratory (JHU/APL) under Goddard's management. A single mission would be selected partway through Phase A; the selected team would continue through the remainder of that phase and toward Key Decision Point B, while teams not chosen would not have to carry their concepts through the rest of Phase A on their own.

The agency gives concrete timeline targets. For Astro-Probes, New Frontiers and Discovery, the period from an Announcement of Opportunity to Step 2 selection is expected to fall from 35 months to about 19.5 months, a reduction of up to 45 percent. MIDEX and Earth Explorer would use a similar two-step model and also target a reduction of up to 45 percent. For SMEX, Missions of Opportunity, Earth Venture, Hosted Payloads and Ride Shares, NASA plans a single-step contest, with final selection falling from about 32 months to about 19 months-a reduction of up to 40 percent. These are proposed schedule targets for the revised process.

MIDEX and Earth Explorer would draw on a wider pool of implementing organizations, including universities and industry partners. NASA would assess organizations' past performance on projects of similar complexity and cost before selection. Principal-investigator-led teams could request pairing with a Goddard or JPL implementation team at Step 1. NASA could also provide Center support to help with procurement, manage contracts or resolve technical challenges quickly.

NASA science also includes research conducted aboard the International Space Station; a Crew-12 research account describes one such orbital mission. CM2.0, by contrast, changes how NASA selects several classes of science missions.

Cost And Capability

The revised competitions would open several mission classes to a broader range of implementing organizations, while smaller competitions would use smaller review teams and virtual site visits. NASA also expects mission teams to adopt commercial capabilities-including buses, subsystems and multi-mission operations-when they offer a technical or cost benefit. The agency says it will continue assessing the commercial landscape, building on its Science as a Service Request for Information.

Cost and schedule controls would remain mandatory across mission classes. Phase A estimates would inform decisions about mission complexity and scope. Breaches of control thresholds could bring consequences up to and including mission termination. NASA says directing work appropriately to Goddard and JPL is intended to reduce unnecessary competition between its Centers, support collaboration and retain critical skills.

NASA will explain CM2.0 and take questions at a virtual NASA Science Town Hall on Monday, October 26, from NASA Headquarters. The agency describes the model as its response to the Administrator's direction to accelerate science delivery and reduce the time and resources spent on long competitions. Separately, SMD plans to release Research Opportunities in Space and Earth Sciences 2027 (ROSES-27) no later than January 2027; the cycle is expected to cover about 50 program areas across astrophysics, biological and physical sciences, Earth science, heliophysics, and lunar and planetary research.

An Announcement of Opportunity is NASA's formal call for proposals. Under the revised approach, the first review would ask whether a mission's science case merits further work before teams undertake more detailed implementation planning. That distinction matters: a Step 1 selection would advance a proposal for study, while the later down-selection would identify the mission to continue through Phase A.