OpenAI plans to invest $30 billion in a hyperscale data center campus in coastal Georgia, with up to 3.2 gigawatts of site power to support advanced AI development and deployment over the next decade.
The proposed campus in Effingham County, Georgia, would rank among the largest artificial intelligence infrastructure projects in the United States, with projected development investment exceeding $30 billion. Known as Project Camellia, the site covers more than 2,600 acres in the Savannah Gateway Industrial Hub. Plans call for four data-center buildings with a combined footprint of about 4.4 million square feet. The project is intended to support the training and operation of advanced AI models as demand for large-scale computing grows.
Infrastructure Scale and Timeline
The campus is planned around a 3.2-gigawatt power connection, with Georgia Power expected to deliver electricity in phases from 2028 through 2032. That figure describes power delivered to the site, not computing capacity alone: servers would share the supply with facility systems, including cooling and power conversion. Networking equipment and electrical losses also draw power. Usable IT load would so be lower than the site-power figure, a distinction that matters when comparing announced projects measured in gigawatts of site power with those reporting GW-IT.
The Georgia Power agreement provides for up to 3.2 GW of new generation capacity to serve the campus. The utility has not publicly identified the generation technologies that would supply the load. OpenAI has said it would provide up to 1 GW of flexible demand response, enabling consumption to be reduced or shifted under specified grid conditions. The project remains a planned, phased development; regulatory approval of the power-supply arrangement does not mean the buildings, generation assets or computing systems are already complete.
OpenAI has described the project as part of a shift toward a more direct role in designing its infrastructure. Earlier initiatives, including the Stargate campus in Texas, involved development partners such as Oracle and SoftBank. The company has also discussed standardized designs for data centers, networking and hardware to support faster deployment. The Georgia campus is among the largest announced AI infrastructure developments, but its full planned scale will depend on successive construction and utility-infrastructure stages.
Energy, Community, and Environmental Commitments
Georgia regulators considered whether Georgia Power could be left with costly infrastructure if OpenAI abandoned the project before completing its reported 25-year contractual commitment. This is the stranded-asset risk: investments made to serve a major customer could otherwise leave costs for other ratepayers. Georgia Power representative Josh Peacock told Georgia Public Broadcasting, “Part of the contractual process is that these data centers will pay for the infrastructure that serves their facility.” The company’s stated position is that customers such as OpenAI should fund infrastructure dedicated to their facilities.
The issue sits within a much larger buildout. Georgia Power estimates that data-center growth across the state may require about $16 billion in upfront spending on power plants, substations and transmission lines. Peacock said the exact infrastructure requirements were still being developed with the customer: “We don’t know what that infrastructure exactly is going to look like yet, as we work with them and to deliver the energy they require.” The eventual effects on the grid and electricity customers will depend on construction progress and the terms governing OpenAI’s long-term commitment.
The project announcement drew opposition from hundreds of local residents, with concerns about local infrastructure, particularly water supplies and electricity demand. OpenAI says the campus will use a closed-loop cooling system and will not divert water from local communities. The company has also held training for local small-business owners. One participating business owner described the discussions as prompting residents to ask “questions, talk to us about their water supply, electricity and all that stuff, what does it mean for us as a community?”
OpenAI has said it will fund infrastructure required to serve the site and use demand-response measures to help manage electricity use. The company has also outlined community commitments, including a community fund and product credits for local students. The project’s eventual effects on water systems, employment and local services will depend on final engineering designs and how the campus is built and operated.
Enterprise Platform and Strategic Positioning
Alongside its infrastructure expansion, OpenAI has introduced Presence, an enterprise software platform designed to connect AI models with internal company data, software and business workflows. The platform is intended to let organizations deploy AI agents for customer support and sales operations, while also handling IT service requests, with the goal of reducing the need for direct human intervention. The strategy combines large-scale computing infrastructure with enterprise software as competition intensifies and access to AI models becomes increasingly commoditized.
OpenAI is betting that control of both physical infrastructure and the software layer will help it maintain a competitive position as rivals improve model performance and lower prices. The long-term reliability and safety of enterprise AI agents will depend on their performance in operational settings. More broadly, the Georgia campus reflects the growing infrastructure demands of AI systems, which rely on clusters of specialized processors and high-capacity networking to train and operate foundation models.
At 3.2 GW of planned site power, Project Camellia would rank among the largest proposed data-center developments globally. The figure should not be read as 3.2 GW of computing capacity: facility systems also consume power, and the usable load available to servers is lower. The project’s projected investment exceeds $30 billion, while the full campus would take shape through staged construction and power deliveries planned between 2028 and 2032.
As with other hyperscale data centers, the project’s environmental and community impact will depend on its electricity supply, water-management practices and engagement with local residents. The Georgia Public Service Commission’s approval advances the power-supply arrangement, while leaving the project’s eventual footprint dependent on construction, engineering and the operation of its long-term electricity commitments. The questions raised in Effingham County also reflect a broader policy challenge as governments weigh the implications for ratepayers of expanding AI infrastructure’s demands on the grid and water supplies.
Modern AI relies on large-scale data centers. Training and operating foundation models, including large language and multimodal systems, requires extensive parallel computing, typically supplied by clusters of specialized processors in purpose-built facilities. Reliable, high-capacity infrastructure is now a central constraint on the pace of AI research and deployment. Project Camellia’s announced scale is a measure of planned development, not capacity already in operation.